After Years of Abandonment, Kamariny Stadium Rises Again as Government Races to Restore Iten’s Athletics Glory Ahead of Mashujaa Day
The project, which began in 2017, experienced serious setbacks before construction resumed under a new contractor. By September 2026, the stadium had reportedly reached 58 per cent completion as the government intensified preparations for the October 20 Mashujaa Day celebrations. Principal Secretary Raymond Omollo is involved in coordinating the wider national celebrations across Elgeyo Marakwet, Nandi and Uasin Gishu counties, although the available reports do not confirm that he personally announced the stadium's latest completion figures. The renewed work has raised hopes that Kamariny will once again serve athletes, schools, coaches and the wider community. Its completion could support talent development, create economic opportunities and strengthen Iten's position as an international athletics destination
The long-awaited restoration of Kamariny Stadium in Iten, Elgeyo Marakwet County, is gathering momentum after years of delays that left the iconic sporting facility incomplete and deprived local athletes of one of their most important training grounds. The national government has renewed efforts to complete the stadium, with construction progressing as Kenya prepares for the 2026 Mashujaa Day celebrations scheduled for October 20.The restoration is part of broader efforts to improve sports infrastructure, nurture athletic talent and create opportunities for young people in a region internationally recognised for producing outstanding long-distance runners. Recent reports indicate that the stadium, which is expected to accommodate approximately 10,000 spectators, had reached 58 per cent completion by September 25, 2026.
Interior Principal Secretary Raymond Omollo has been involved in coordinating preparations for the national celebrations across Elgeyo Marakwet, Nandi and Uasin Gishu counties. However, the latest publicly available reports reviewed for this article do not establish that Omollo personally announced the specific construction progress at Kamariny Stadium. His role in the wider preparations should therefore be distinguished from the work being implemented by the sports authorities and construction teams.The renewed construction has raised hopes among athletes, coaches, residents and sports stakeholders that Kamariny Stadium will eventually regain its reputation as a major athletics centre and provide modern facilities for training and competition.
A Stadium With a Rich Sporting History
Kamariny Stadium is located near Iten town, the headquarters of Elgeyo Marakwet County. It occupies a special place in Kenya's sporting history because of its association with the country's celebrated distance-running tradition.
Iten is widely recognised as an international destination for elite athletes who travel to the region to train at altitude. The area's high elevation, established running culture and experienced coaches have helped attract both Kenyan and international athletes preparing for major competitions.For many years, Kamariny provided an important space where athletes could train, improve their endurance and prepare for national and international races. Its reputation extended beyond the local community because the region has produced some of Kenya's most successful distance runners.
The stadium's importance was not limited to professional athletes. It also served aspiring runners, schoolchildren, coaches and community members who depended on the facility for sports development.
The planned modernisation was intended to transform the stadium into a contemporary sporting complex with improved spectator facilities and an upgraded athletics track. However, the project experienced prolonged delays, leaving the facility unable to fulfil its intended purpose for several years.Construction and modernisation works at Kamariny Stadium began in 2017, with the government intending to upgrade the facility to modern standards. The initial project included a pavilion, changing rooms, medical rooms, offices, pitch improvements and athletics track works.
According to a report by the Auditor-General on Sports Kenya for the financial year ending June 30, 2019, the original contract was valued at approximately KSh287.8 million. The works were scheduled to begin in January 2017 and finish by May 2018.
However, an inspection in March 2019 found that the pitch and track works had not started and that the contractor had abandoned the site. The audit report also recorded payments of approximately KSh160.7 million to the contractor by June 2019.In January 2021, the Elgeyo Marakwet County Government reported that Sports Cabinet Secretary Amina Mohamed had indicated that a new contractor would be identified to accelerate the work. The county's announcement acknowledged that the stadium had fallen behind schedule.
The repeated delays meant that athletes had to seek alternative training arrangements while residents waited for the promised modern facility.The prolonged suspension of construction had consequences for the local sporting community. Kamariny was expected to be a major centre for athletics, but the incomplete facility could not provide the full range of services planned under the modernisation programme.
In February 2023, the Elgeyo Marakwet County Government announced that Governor Wisley Rotich had ordered grading, levelling and watering of the stadium track to improve its condition after the works to transform it into a tartan track stalled.
The governor said the temporary improvements would allow athletes to return to training as the county awaited the national government's completion of the stadium. The county also promised routine maintenance of the field. At the time, the administration reported that more than 2,000 athletes had previously used the stadium for training. The renewed construction was a significant development after years in which the stadium remained incomplete. It offered hope that the project could finally move beyond repeated announcements and deliver the infrastructure athletes had been waiting for.
Progress continued into 2026 as preparations intensified for Mashujaa Day, which will be celebrated on October 20. The government has been working to improve facilities across Elgeyo Marakwet, Nandi and Uasin Gishu counties as part of the regional preparations.
According to reporting published in June 2026, the government accelerated work at Kamariny to meet the anticipated October deadline. The renewed urgency was linked to the planned national celebrations and the opportunity to showcase the region's sporting heritage.Principal Secretary Raymond Omollo, who serves in the State Department for Internal Security and National Administration, is among the senior government officials coordinating preparations for the 2026 Mashujaa Day celebrations.
The celebrations are particularly significant because Elgeyo Marakwet, Nandi and Uasin Gishu counties are jointly involved in hosting activities leading up to the national event. The programme provides an opportunity to highlight the region's contributions to athletics, economic development and national life.
In a September 25 update, Omollo said preparations were progressing across the three counties. The programme includes infrastructure improvements and activities under the theme of security, sports and the finance sector. However, it is important to clarify that Omollo's documented role in coordinating national celebrations does not, by itself, establish that he is directly supervising the stadium's construction. The sports authorities and the agencies responsible for implementation remain central to delivering the project.
His involvement in the broader preparations nevertheless reflects the importance the government has attached to ensuring that infrastructure and event arrangements in the region are ready for the national celebrations.
The occasion also creates an opportunity for government officials to assess whether projects announced to the public are progressing according to schedule and whether they will provide lasting benefits after the celebrations conclude.The stadium is designed to accommodate approximately 10,000 spectators, making it an important addition to Kenya's sporting infrastructure.
The reported completion figure indicates that significant work remains before the facility can be considered fully finished. Although construction has resumed, the outstanding works must be completed to ensure that athletes and spectators can use the stadium safely.
The remaining tasks may include finishing and checking the athletics facilities, spectator areas and supporting infrastructure, depending on the outstanding items under the construction contract. These should be treated as areas requiring verification rather than a confirmed list of unfinished works.The restoration of Kamariny Stadium is expected to create opportunities beyond the sporting sector. Once fully operational, the facility could attract athletics competitions, training camps, sports tourism and other events that bring visitors to Elgeyo Marakwet County.
Iten already attracts runners from different parts of Kenya and abroad because of its altitude and established athletics culture. A modern stadium would strengthen the town's ability to accommodate organised training and competitions.
Local businesses could benefit from increased demand for accommodation, meals, transport, sports equipment and other services. Hotels, restaurants, small shops and transport operators may experience higher activity when the stadium hosts major events.One of the most important expected benefits of restoring Kamariny Stadium is improved access to sporting facilities for young athletes.
Kenya has built a strong international reputation in distance running, but the development of future champions depends on access to training grounds, qualified coaches, medical support and organised competitions.
A properly equipped stadium could help schools and athletics clubs conduct training sessions and competitions in a more structured environment. It could also provide a venue where emerging athletes demonstrate their abilities before coaches and talent scouts.
Young people who aspire to compete at national and international levels would benefit from having a modern facility close to home rather than relying entirely on alternative venues.Despite the progress reported in 2026, the history of Kamariny Stadium demonstrates the risks associated with prolonged delays in public infrastructure projects.
The initial construction schedule was missed, and the project remained incomplete for years. The experience underlines the importance of effective contract management, regular inspections, timely payments and clear communication between implementing agencies and the public.
As construction continues, residents will expect the responsible authorities to provide transparent updates on the remaining work, the expected completion date and the final cost.The government must also ensure that the stadium is delivered to the required safety and quality standards. Rushing construction to meet a national celebration deadline should not come at the expense of durability, accessibility or the safety of athletes and spectators.
Equally important is the need to provide for maintenance after the facility opens. Athletics tracks and other sporting infrastructure require regular care to preserve their condition and prevent the public from losing access to the investment through neglect.
A clear management plan, adequate maintenance funding and a calendar of sporting events would help protect the stadium's long-term value.